INSTALLATION PREPARATIONS

< Previous Next >

2016 – MX-5 – General Information

INSTALLATION PREPARATIONS

Rough Cutting of New Parts

  • For cut–and–join areas, allow for an overlap of 30—50 mm {1.2—1.9 in} with the remaining area on the body side and then rough–cut the new parts.

Determination of Welding Method

  • If the total thickness at the area to be welded is 3 mm {0.12 in} or more, use a gas shielded–arc welder to make the plug welds.

Making Holes for Arc Welding

  • For places that cannot be spot welded, make a hole for arc welding using a punch or drill as follows.

(mm )

Panel thickness (φ)

Hole diameter (φ)

0.60—0.90 {0.024—0.035}

5.0 {0.20}

0.91—1.20 {0.036—0.047}

6.0 {0.24}

1.21—1.80 {0.0477—0.0708}

8.0 {0.31}

1.81—4.50 {0.072—0.177}

10.0 {0.394}

  • Grind the shaded section indicated in the diagram below and create a hole in the part where the 3—4 plates are put together. Also, weld the plates together tightly so that gaps do not develop.

Application of Weld–through Primer

  • For treatment against corrosion, remove the paint grease, and other material from the portion of new part and body to be welded, and apply weld–through primer.

< Previous Next >